20Cost–Benefit Analysis
A government deciding whether to build a bridge, regulate a chemical or fund a programme needs a common unit for what it costs and what it gives. Cost–benefit analysis supplies one: money, measured by what people would be willing to pay. This chapter states the method, measures the two numbers on which most analyses turn — the discount rate and the value of a statistical life — and sets the forecasts of large projects against their outcomes.
Across 258 projects, actual construction costs exceeded the estimates on which the decision to build was made by 27.6 % on average: 44.7 % for rail, 33.8 % for bridges and tunnels, 20.4 % for roads. Costs were underestimated in almost nine projects out of ten. Errors with no systematic cause would scatter around zero; these lean one way, whether from optimism or from strategic misstatement.
You already know
The grades 10–12 volume defined present value and discounting. The Year 1 volume defined the compensating and equivalent variations, and the Year 2 volume the compensation tests and expected utility. Chapter 5 of this volume estimated the value of travel time from commuters’ choices, and chapter 17 defined the marginal cost of public funds.
Notation 20.1 (Symbols of this chapter)
and are benefits and costs in year ; a discount rate; a risk of death; the net present value.
20.1 Willingness to pay and accounting prices
Definition 20.2 (Cost–benefit analysis; accounting price)
Cost–benefit analysis values all the effects of a project in money, as the sum over the people affected of what they would pay for the gains or accept for the losses, discounts them to the present, and accepts the project if the net present value is positive. An accounting price is the value of a resource used in such an appraisal when its market price does not measure its cost to society.
Proposition 20.3 (The net-present-value rule and compensation)
If each person’s gain is measured by the compensating variation and money can be transferred between people at no cost, a positive net present value means the gainers could compensate the losers and remain better off.
Proof. The compensating variation of each gainer is the most she would pay, and of each loser the least he would accept, for the project. A positive sum means the gainers’ total willingness to pay exceeds the losers’ total compensation: paying each loser his compensation leaves every gainer at least as well off as without the project, and some strictly better. ∎
The rule does not say the compensation is paid; it applies the Year 2 volume’s compensation test, and inherits its limits. Where transfers are costly, a dalen raised to pay for a project costs society the marginal cost of public funds of chapter 17, and the benefits must clear that bar.
Accounting prices correct market prices that do not measure costs. A worker hired from unemployment costs the economy less than her wage: the output she would otherwise have produced, plus the value of the leisure she gives up. Imported steel bought under a tariff costs the economy its world price, not the price paid inside the tariff wall; the tariff is a transfer to the government.
Definition 20.4 (Marginal value of public funds)
The marginal value of public funds of a programme is its beneficiaries’ willingness to pay for it divided by its net cost to the government, counting the taxes its behavioural effects raise or lose.
The ratio compares programmes of any kind on one scale: a programme whose effects raise future tax revenue enough to pay for itself has a net cost of zero or less, and an infinite value.
On the record — The marginal value of public funds of 133 policies
Hendren and Sprung-Keyser computed the ratio for 133 changes in United States policy over half a century — social insurance, education and training, taxes and cash transfers, transfers in kind — from the published estimates of each policy’s effects. Direct spending on the health and education of low-income children had the highest values, above 5 on average. Policies aimed at adults were generally between 0.5 and 2. Each value rests on the studies it is built from, and inherits their grades.
20.2 Discounting
Definition 20.5 (Social discount rate)
The social discount rate is the rate used to convert future benefits and costs into present values in a public appraisal: .
make\_pv.py)A dalen in 100 years is worth 0.25 today at 1.4 %, 0.05 at 3 % and 0.001 at 7 %. For a project whose benefits come in a decade, the choice among these rates matters little; for one whose benefits come in a century — a climate policy, a nuclear waste store — it decides the answer. The rate has two candidate sources: the return that capital earns at the margin, which is what the funds would yield elsewhere, and the rate at which society is willing to trade consumption now for consumption later. They differ by the taxes and risk premiums between them, and choosing between them is a choice the evidence does not make.
Facts as of 2026
HM Treasury’s appraisal guidance for the United Kingdom discounts at 3.00 % a year in real terms for years 1 to 30, 2.50 % for years 31 to 75 and 2.25 % from year 76 (Green Book, revised 28 October 2026). The United States Environmental Protection Agency values a statistical life at 7.4 million dollars of 2006, updated to the prices of each analysis. The chart’s 1.4 %, 3 % and 7 % span the rates in use and in debate.
Proposition 20.6 (Declining certainty-equivalent rates)
If the discount rate is or for ever, each with probability one half, the certainty-equivalent rate , defined by , falls with the horizon and tends to .
Proof. Write the right side as . Then . At the expected discount factor’s slope gives ; as grows, and the second term is . In between, falls because the state with the low rate carries a growing share of the expected discount factor. ∎
Uncertainty about the rate thus argues for lower rates at long horizons, because it is the expected discount factor, not the expected rate, that weighs a future dalen.
20.3 The value of a statistical life
Definition 20.7 (Value of a statistical life)
The value of a statistical life is the willingness to pay for a small reduction in the risk of death divided by that reduction: what a group would pay, in total, for measures that prevent one death among them, none of whom knows who it will be.
Proposition 20.8 (The value of a statistical life from expected utility)
A person with wealth , risk of death and utility if alive (zero if dead) will pay for a reduction in the risk with : the value of a statistical life.
Proof. Expected utility is . Holding it constant, , so a fall in of is worth . ∎
The value rises with wealth (through ), so richer people pay more for the same safety: one reason agencies use one value for everyone rather than one per income.
Model — Hedonic wages and the value of a statistical life
Assumes. Workers know the fatal risks of jobs and choose among them in competitive labour markets; employers pay more for riskier jobs to attract workers.
Predicts. Wages rise with fatal risk, other job attributes held constant; the premium per unit of risk is the marginal worker’s value of a statistical life.
Tested. A review of more than 60 studies of mortality risk premiums in ten countries finds the premium, and finds that the value of a statistical life rises with income with an elasticity of about 0.5 to 0.6.
Breaks. Workers misperceive small risks; people who mind risk least sort into dangerous jobs, so the premium measures their value, not the population’s; and risky jobs differ from safe ones in attributes no data record, which bias the premium either way.
How it is measured — The value of a statistical life in practice
A wage premium of 1,000 dalens a year for an extra fatal risk of 1 in 10,000 a year implies a value of 10 million dalens. Agencies publish one value for their appraisals and update it with prices and incomes, as the dated box above shows for one of them; the value of a project’s safety benefits is the deaths it avoids times that value.
20.4 Risk and revealed or stated preferences
Definition 20.9 (Hedonic wage method; travel-cost method; contingent valuation)
The hedonic wage method infers the value of a job attribute, such as safety, from the wage differences it commands. The travel-cost method infers the value of a site from what visitors spend in money and time to reach it. Contingent valuation asks people in a survey what they would pay for a good that is not sold.
Risky outcomes are valued at their expected values when the risks are spread over many people or many projects, as most public risks are; a project whose failure would hit the whole economy at once carries a cost of risk on top.
Open question — Can a survey value what is not sold?
Some goods — a wilderness nobody visits, a species — have no market and leave no trace in behaviour, so only a survey can value them.
- One survey of the evidence finds three standing problems: answers to hypothetical questions overstate what people pay when the payment is real; what people would pay to gain a good differs widely from what they would accept to lose it; and values do not grow with the scope of the good (saving one lake is valued like saving ten). Grade 2: experiments comparing hypothetical with real payments, but for goods unlike those the method is used for.
- Another holds that well-designed surveys give usable values where nothing else does, as for the damage of the 1989 Exxon Valdez oil spill, and that leaving such goods out of an appraisal values them at zero, a worse error. Grade 4: an argument about the alternative, without a test of the values.
20.5 Forecasts against outcomes
Definition 20.10 (Optimism bias; reference-class forecasting)
Optimism bias is the systematic tendency of project forecasts to understate costs and overstate benefits. Reference-class forecasting corrects a forecast by the distribution of outcomes against forecasts in a class of past projects of the same kind.
The overruns of the opening chart differ by region: 34.2 % for rail in Europe, 40.8 % in North America and 64.6 % elsewhere; for roads, 22.4 % in Europe and 8.4 % in North America. A reference-class correction raises a rail estimate by the class’s average overrun — or, to be safe with a given probability, by a high percentile of the class’s distribution — before the appraisal. It does not explain why the forecasts were low; it removes the bias whatever its cause.
On the record — Forecasts of demand
Benefits are forecast too, and the same authors audited the traffic forecasts of 210 transport projects in 14 countries. In nine rail projects out of ten, passenger numbers had been overestimated, by 106 % on average: the forecast was about twice what came. For half of the road projects, traffic differed from its forecast by more than 20 % either way, with no lean. Neither kind of forecast had become more accurate over thirty years. Rail projects thus combined costs a half above their estimates with half the forecast passengers: if benefits scale with passengers, an appraisal built on both forecasts overstated the benefit–cost ratio about threefold ().
20.6 Exercises
Exercise 20.1 ★
In the opening chart, which type of project overruns most, and where? What share of projects overran?
Solution
Solution of Exercise 20.1.
Rail, by 44.7 % on average, and most outside Europe and North America (64.6 %, 16 projects). Costs were underestimated in almost 9 projects out of 10 (86 %).
Exercise 20.2 ★
A bridge costs 100 million dalens today and yields 6 million a year for 30 years, from next year. Find its net present value at 3 % and 7 %.
Solution
Solution of Exercise 20.2.
The annuity factor for 30 years is 19.60 at 3 % and 12.41 at 7 %. NPV: million at 3 %; million at 7 %.
Exercise 20.3 ★
Workers accept a fatal risk higher by 1 in 10,000 a year for 1,000 dalens more pay a year. Find the value of a statistical life. What is it if the premium is 800?
Solution
Solution of Exercise 20.3.
million dalens; with a premium of 800, 8 million.
Exercise 20.4 ★
What data on forecasts would distinguish random errors from optimism bias?
Solution
Solution of Exercise 20.4.
Random errors would average zero and be as often above as below; optimism bias shows in a mean overrun above zero, overruns far more frequent than underruns, and no improvement as forecasters learn from past projects.
Exercise 20.5 ★★
A project hires 100 workers at 30,000 dalens a year. Sixty would otherwise be unemployed, valuing their leisure at 8,000 a year; forty would leave other jobs where they produced 30,000. Find the accounting cost of the labour.
Solution
Solution of Exercise 20.5.
million dalens a year, against a wage bill of 3 million.
Exercise 20.6 ★★
The discount rate is 1 % or 5 %, with equal probability, for ever. Compute the certainty-equivalent rate at 10, 50 and 200 years.
Solution
Solution of Exercise 20.6.
With continuous rates, : 2.80 % at 10 years, 2.13 % at 50, 1.35 % at 200, falling toward 1 %.
Exercise 20.7 ★★
A climate-type project costs 10 today and yields 100 in year 100. For which discount rates is it worth doing?
Solution
Solution of Exercise 20.7.
Worth doing if , that is : .
Exercise 20.8 ★★
A rail project is forecast to cost 2 billion dalens. Correct the forecast with the rail averages of the opening chart for Europe and for all regions, and say what a correction to the 80th percentile would need.
Solution
Solution of Exercise 20.8.
With the European rail average, billion dalens; with the all-region rail average, billion. The 80th percentile needs the distribution of overruns, not only its mean; if rail overruns were normal with the published standard deviation of 38.4 points, it would be , or 3.54 billion.
Exercise 20.9 ★★
What evidence would show that stated willingness to pay is biased?
Solution
Solution of Exercise 20.9.
Stated amounts that exceed what the same people pay when the payment is real; values that do not rise with the quantity of the good offered; and large gaps between what people would pay to gain a good and accept to lose it.
Exercise 20.10 ★★★
Prove the declining-rate proposition, and show that is strictly decreasing.
Solution
Solution of Exercise 20.10.
The limit is in the text. Let , so . As a mixture of exponentials, the discount factor is log-convex: , because is the variance of the rate under weights proportional to , positive since . With , is concave with , so is strictly decreasing.
Exercise 20.11 ★★★
Simulate 5,000 workers whose log wage depends on schooling, experience and a job’s fatal risk, with a premium of 0.02 log points per extra death in 10,000, at a mean wage of 30,000 dalens. Estimate the hedonic wage regression and the value of a statistical life, then add an unrecorded job attribute correlated with risk and show the bias.
Solution
Solution of Exercise 20.11.
The tested solution is ex11_hedonic.py, in the chapter’s exercises/ folder. With all attributes recorded the premium is 0.0170 log points (s.e. 0.0042), a value of a statistical life of 5.09 million dalens against a true 6 million. Leaving out an attribute that is worse in risky jobs raises it to 0.0566 and 17.0 million: the premium for risk absorbs the premium for unpleasantness.
Exercise 20.12 ★★★
Programme A costs 100, raises 20 in later taxes, and its beneficiaries would pay 120 for it. Programme B costs 100, loses 10 in taxes through lower work, and its beneficiaries would pay 90. Find each one’s marginal value of public funds and rank them.
Solution
Solution of Exercise 20.12.
A: . B: . A delivers more value per dalen of net cost; B delivers less than a dalen per dalen.
20.7 Problem: A New Bridge for Brenmoor
Problem 20.1
Weekend problem — A new bridge for Brenmoor
Brenmoor, Brenland’s capital, plans a bridge forecast to cost 120, 160 and 120 million dalens in years 0, 1 and 2. It opens in year 3 and is appraised over 40 years of use, with maintenance of 4 million a year. It will carry 30,000 vehicle trips a day, each saving 10 minutes for 1.2 occupants, valued at 13.1 dalens an hour (the value of travel time of chapter 5). It is expected to avoid one road death a year, valued at 3 million dalens.
Part I — the benefits.
- Compute the hours saved in a year.
- Value them.
- Why use commuters’ own value of time rather than their wage?
- Compute the safety benefit.
- Compute the net annual benefit after maintenance.
- Which effects of a bridge does this list leave out?
Part II — safety.
- How would a hedonic-wage study produce the 3 million?
- What would the safety benefit be with a value of 6 million?
- Why should every death avoided carry the same value, whoever travels?
- Workers in risky jobs may mind risk least. Which way does that bias the value?
Part III — discounting.
- Write the net present value as a sum over years.
- Compute it at 2 %, 3.5 % and 7 %.
- Find the discount rate at which it is zero.
- Explain why the NPV falls with the rate for this project.
- Which rate would you use, and why does the choice matter here?
- The net-present-value chart below plots both cases of Part IV. Read off where each crosses zero.
Part IV — a reference-class correction. Bridges and tunnels overran their estimates by 33.8 % on average.
- Correct the construction cost.
- Recompute the net present value at 2 %, 3.5 % and 7 %.
- Find the new rate at which it is zero.
- Should traffic forecasts be corrected too? What would that do?
- The money is raised by taxes with a marginal cost of public funds of 1.3. How does that change the test?
- Why might the forecasters’ estimate be low in the first place?
- What would make the correction itself wrong for this bridge?
- Who gains from the bridge, and who pays?
- State the result: the bridge’s net present value after the correction, at 3.5 %, and the discount rate at which it turns negative.
Solution
Solution of Problem 20.1.
1. hours.
2. million dalens a year.
3. The benefit is what travellers would pay for the time, which their choices reveal; much of the time saved is not working time and is not valued at the wage.
4. million a year.
5. million a year.
6. Traffic induced by the bridge, effects on other routes, noise and land use, vehicle operating costs, and the time lost during construction.
7. By estimating the wage premium of jobs with higher fatal risk and dividing it by the difference in risk.
8. 6 million a year; the net annual benefit rises to 30.7 million.
9. The deaths avoided are statistical: nobody knows who will be saved, and the appraisal values the safety of all travellers alike rather than by income.
10. Downward: the measured premium is that of people who mind risk least.
11. , with costs 120, 160, 120 in years 0–2 and net benefits 27.7 in years 3–42.
12. 335.8 million at 2 %, 165.4 at 3.5 %, at 7 %.
13. 5.86 %.
14. The costs come first and the benefits later: a higher rate shrinks the later benefits more than the early costs.
15. The answer turns on it: positive at 2 % and 3.5 %, negative at 7 %. A rate close to the return the funds would earn elsewhere if they displace investment; closer to the rate of time preference if they displace consumption.
16. About 5.9 % with the forecast cost, about 3.9 % with the corrected one.
17. million.
18. 203.3 million at 2 %, 34.7 at 3.5 %, at 7 %.
19. 3.90 %.
20. Yes, if traffic forecasts for such projects are also biased; correcting them lowers benefits, the NPV and the break-even rate further.
21. Each dalen of cost counts 1.3: at 3.5 %, benefits of 631.7 million in present value against corrected costs (construction and maintenance) of 597.0 give million. The bridge no longer passes.
22. Promoters who want the project built, and appraisals that reward low estimates; and genuine uncertainty that is treated as if it were not there.
23. A bridge unlike the reference class — a simple, short span, or a fixed-price contract that moves the risk to the builder.
24. Travellers and nearby land owners gain; taxpayers pay, and the excess burden of the taxes adds to the cost.
25. After the correction, the bridge’s net present value at 3.5 % is 34.7 million dalens, and it turns negative at discount rates above 3.9 %.