Computer Science · 术语表

什么是 Critical path?

Definition 25.10 University Computer Science — Year 1 · 第 25 章 — Shortest Paths

A project is a set of tasks with durations and prerequisites, which form a DAG. The earliest start of a task is the largest total duration of a chain of tasks that must precede it; a critical path is a chain of tasks of largest total duration: its length is the shortest possible duration of the project.